Project cost: $22.8 million
Construction start: 2024
Estimated completion: 2026

PATCO Woodcrest Platform & Collingswood Headhouses Upgrades

Project Overview

As part of our ongoing commitment to modernizing PATCO stations, we are investing in significant upgrades at Woodcrest and Collingswood Stations to enhance safety, accessibility, and the overall rider experience.

The project, with a total investment of $22.8 million, is currently in the construction phase, which started in 2024 and is expected to be completed in 2026.

The Woodcrest Station improvements focus on replacing the two aging concrete platforms, expanding the headhouses (enclosed structures on the platforms), and enhancing the paid area of the station. These upgrades will modernize the station while maintaining its role as a key station for PATCO.

At Collingswood Station, both headhouses will be replaced with new, modern enclosures featuring upgraded lighting, improved windows, necessary concrete repairs, and an overall refresh of the platform level.

Both stations' headhouses date back to their original construction—Woodcrest from the late 1970s and Collingswood since its opening in the late 1960s. This project will bring them in line with the recent upgrades completed at Ferry Avenue, Westmont, and Lindenwold Stations, creating a better experience for our riders.

These improvements reflect the Authority's ongoing commitment to maintaining and enhancing our facilities for future generations.