TRAVEL ADVISORIES

Below are our scheduled lane configurations due to scheduled maintenance work. Schedule times are approximate and may change without notice due to operational needs and inclement weather. In addition, there may be times when an unexpected or unscheduled lane closure occurs. Always obey speed restrictions when driving through work zones.

Benjamin Franklin Bridge

Travel Information:
Monday through Friday
Morning rush (5 a.m. to 9 a.m.) - 3 lanes to NJ and 4 lanes to PA
Off-peak (9 a.m. to 3:30 p.m.) - Minimum 2 lanes each direction
Evening rush (3:30 p.m. to 7 p.m.) - 4 lanes to NJ and 3 lanes to PA
Evening (8 p.m.- 10:30 p.m.) - 3 lanes to NJ and 2 lanes to PA


Pedestrian Walkway

North Walkway: OPEN DAILY
South Walkway: CLOSED
(Under construction with $8 million in upgrades. Learn more.)


Walt Whitman Bridge


Please note the lane closure schedule listed below can be adjusted as needed to accommodate inclement weather and scheduled events at the South Philadelphia stadiums.

Monday through Friday
• 6:00AM to 9:30AM-4 lanes open to PA and 2 lanes open to NJ.
• 9:30AM to 2:30PM-2 lanes open to PA and 2 lanes open to NJ.
• 2:30PM to 7:00PM-2 lanes open to PA and 4 lanes open to NJ.
• 7:00PM to 6:00AM-4 lanes open to PA and 3 lanes open to NJ.

Saturday through Monday
•    6:00AM to 7:00PM – 3 lanes open to PA and 3 lanes open to NJ.
•    7:00PM Saturday through 6:00AM Monday – 4 lanes open to PA and 3 lanes open to NJ.


Commodore Barry Bridge


Monday through Friday
• 4 a.m. to 3 p.m. - 2 lane(s) to NJ and 1 lane(s) to PA.
Scheduled construction work: deck repair, pot hole repairs, and painting project.


Betsy Ross Bridge

Monday through Friday
• Minimum of 2 lanes in each direction