Project cost: $45.4 million
Design consultant: HNTB
Contractor: Railroad Construction Company of South Jersey
Completion: January 2020

PATCO LINDENWOLD YARD REHABILITATION

Project Description

This project upgraded the condition of approximately 25,000 linear feet of track, 49 yard switches, 750 feet of viaduct track, as well as signal, communication, and power improvements in the yard. The work also included replacement of 2,200 linear feet of 2.4kV and 26.4kV cables along the south pole line adjacent to the Conrail tracks in Camden. These components are part of the original construction from PATCO's opening in 1969, as well as yard expansion in 1978.